Walter Segal (1907-1985) was a Berlin-born architect who emigrated to England in the 1930s and, in the 1960s, devised the Segal Method of self-building using timber-frame construction. Designed to be simple enough for ordinary people to build their own homes – even without building experience – it is also a minimalist and rational approach to architecture.
[edit] Background
In 1962, Segal needed temporary accommodation for his family in North London and used his system to build a house with paving-slab foundations in just two weeks at a materials’ cost of £800 (around £12,000 at today’s prices). His aim was to ensure that after use, the house could be easily dismantled and the materials recycled or sold. Two of Segal’s major projects in London include houses at Segal Close and Walter’s Way.
These projects were followed by a succession of private clients impressed by the speed and economy of the system, not to mention numerous architects who have used Segal’s method for themselves or their clients. The system was also adopted by Lewisham Council in the 1970s and many examples exist in that borough. More exposure has been given by recent TV shows such as Grand Designs and the general growing popularity of self-build in the UK.
[edit] Principles of the Segal Method
Segal’s method involves simply-constructed timber frames with bolted connections which eliminate wet trades such as bricklaying and plastering. The system has been designed to ensure that potentially problematic construction issues such as tolerances and thermal movement are accommodated without complex construction details.
In summary, the principles of the Segal System are:
- A pervasive attitude of rigorous simplification.
- Timber, bolt-together, post-and-beam-based construction.
- The majority of the work can be undertaken by a single person with basic carpentry skills (although assistance may be required for roofing and services).
- The use of only basic tools e.g hammer, saw, plane, spade, drill/driver, tape measure etc.
- Use of readily-available materials in standard sizes, so there is minimal cutting and waste.
- Typically, 600mm x 600mm concrete pad foundations under posts, so strip foundations are not required, and concrete usage is reduced by around 20%.
- No oversite concrete is used – the ground floor stands above the ground.
- No wet trades are required.
- Can accommodate higher insulation levels.
- Easy to extend.
- Proven to work up to three storeys.
- Can achieve Passivhaus or zero-carbon levels.
As a result, large savings in build costs can be achieved.
In devising the system, Segal rethought the build process from first principles to incorporate ways of dealing with fundamental problems such as thermal expansion and tolerances. Working to standard material sizes, organisation and construction are facilitated by the use of a grid layout.
Because the system is predicated towards self-build and those with few construction skills, component assembly is based on dry joints using simple bolts and screws. The process is further simplified by the drawings required – they can typically be hand-drawn diagrams of the layout and structure. However, as with ordinary houses, planning approval and building regulations approval will generally be required.
Various configurations can be constructed, including one or two-storeys, flat- or pitched-roofs, double-height spaces, split levels and courtyards.
[edit] Appendix
[edit] Photographs taken during construction
• Photographs showing the Segal Method in action.
[edit] Typical drawings
|
|||||
|
• Drawings from a case study of the Segal Method by Norman Fellows.
[edit] Videos - 'How to build a Walter Segal house'
• Two step-by-step videos showing how to build a Walter Segal house - VID_0082: Steps 1 to 4 and VID_0085: Steps 5 to 8 - both courtesy of Norman Fellows.
[edit] Related articles on Designing Buildings
- Britain's greatest maverick building.
- Building an extension.
- Building of the week series.
- Community right to build.
- Cul-de-sac.
- Custom-build homes.
- Dennis Severs house.
- Interview with Kevin McCloud.
- Open House London 2017.
- Self-build homes.
- Self-build home project plan.
- Walter Segal: self-built architect.
- Walter Way and Segal Close.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
I'm looking at the Segal method to produce a really low-impact, inexpensive, environmentally advanced (e.g. solar panels on sloping roofs) series of buildings around a proposed lido. Do you know if anyone else has used the method for anything other than housing? We need changing rooms, a cafe, probably some sort of plant room. I'm pretty confident I could design it but it would help persuade the local authority if there are existing examples. Any help/advice would be gratefully received. Thank you.
Judith Martin
Hi Judith
I suggest you contact the others (eg Lewisham, Brighton) who have built using Segal.
I am sure the method can be adapted to suit your needs. I'm curious why you need to persuade the local authority - are they funding?